The Top numbers for each box are the Early Start numbers and the Bottom
$ 15.00


Page:of 2

 

 

                                             Automatic Zoom                                             Actual Size                                             Page Fit                                             Page Width                                                                                          50%                                             75%                                             100%                                             125%                                             150%                                             200%                                             300%                                             400%                                         

 

 

Project Management Old Exam Questions Answers

This Is a Constructed Project Network for problems 1

-

5

(The Top numbers for each box are the Early Start numbers and the Bottom numbers for each box are

the Late Start numbers.)

END

END

1.

I. A

-

C

-

F is

false

because these three tasks are never connected as seen above.

II. B

-

D

-

G is

True

because these three tasks are connected as seen above.

III. B

-

E

-

F

-

G is

True

because these three tasks are connected as seen above.

This leave you with the

answer of D

.

2.

It would take

18 days

as seen above highlighted in yellow.

3.

Activity

Late Start

Early Start

Slack

Where the number

s

came from is

highlighted in red

.

4.

The late start time for C is shown

in the above diagram in Green which is 11

.

A 0 3

3 8 11

C 3 4

1

11

12

G 12

18

6 12 18

D 6

8

2 10

12

E 6

7

1

6

7

B 0 6

6 0 6

F 7

12

5 7

12

H

7

9

2

16

18

H

16

7

9

 

Thanks for rating! Rate 2 more documents to earn a free unlock.

 

 

5.

A).

This wouldn’t work

. This is because you need to use “the Early Start Time Rule” which states

the ES time of an activity is equal to

the largest EF ti

mes of all

the activities that immediately

precede it. If you are taking a day away from task A it will result in shortening task C which will

not effect the end result since Task C is not the largest EF time of C, D and F.

This is Not the

correct answer

.

B). This would Work. Task B is connected to the largest EF time Task F and connected to the

critical path. This is

the correct answer

because It is the cheapest amount that would shorten

the overall length of this project by one day.

C). This woul

d Work

in shortening the task by one day

. Task

D

is connected to the largest EF

time Task F and connected to the critical path

and would shorten the overall length of this

project by one day

. This is

Not the

correct answer

because It is

more expensive th

an option B.

D). This would Work in shortening the task by one day. Task F is the largest EF time and

connected to the critical path and would shorten the overall length of this project by one day.

This is

Not the

correct answer

because It is more ex

pensive than option B.

E). This would Work in shortening the task by one day. Task G is connected to the largest EF

time Task F and connected to the critical path and would shorten the overall length of this

project by one day. This is

Not the

correct

answer

because It is more expensive than option B.

6.

I. This is

False

because task B is the longest task in the project.

II. This is

True

. There is only one project worked on in the first day and that is task A.

III. This is

True

for days 14, 15, and 16, the life of task E, you will also be working on task F.

7.

Its B.

The last task completed on this project, task F, is completed on day 17.